Guide
Commercial build-outs in Austin
What stands between a signed lease and opening day for a build-out or tenant finish-out inside Austin’s city limits, in the order it comes.
Each rule here links to the official page it comes from. Rules and forms change, and city staff decide what a project needs, so confirm the details for your space with Austin Development Services. Its Development Process Team takes short appointments with small business owners and renters about the commercial process.
How we can help with your build-out
Business owners and tenants hire us as the general contractor for build-outs and tenant finish-outs.
On commercial work, you or your architect submits the application and answers the city’s review comments, and we pull the permit as the general contractor.
AGC Design is registered with the City of Austin as a general contractor.
From lease to opening
The city approves the work and issues the certificate of occupancy. On covered buildings at or above a cost threshold, the state runs its own accessibility review and inspection. Each step links to its section.
-
You
Check that the zoning allows your use, get the space’s certificate of occupancy, and look up its permits.
-
Before the permit application goes in
City of Austin
Site plan, correction, or exemption
One of the three, approved. A change of use may go through a site plan exemption.
State of Texas
For a covered building where the estimated construction cost is at least $50,000, the plans go to the state.
-
City of Austin
Building permit and plan review
The application, the review comments, and updates until every reviewer approves.
-
City of Austin
The general contractor activates the building permit. The trade permits can be activated after it.
-
City of Austin
Pre-construction meeting and inspection
Construction and the trade inspections start after it.
-
City of Austin
Pre-foundation, framing and interior, and final inspections, as your permit lists them.
-
City of Austin
Issued when every inspection has passed. A temporary certificate may let you stock or occupy first.
-
State of Texas
Due by the first anniversary of the date construction is completed.
Before you sign the lease
Find out what the space allows before you commit to it. Four questions come first.
Does the zoning allow your use?
Zoning decides which uses a property allows. Look the address up in the city’s Property Profile map for its zoning, then check that district’s permitted uses in the Land Development Code. For an official answer, the city issues a zoning verification letter, which confirms the property’s current zoning and, depending on the request, may note permitted uses.
What does the certificate of occupancy say?
A certificate of occupancy (CO) is the city’s confirmation that a structure is habitable for its legal use and property type and meets the housing and building codes. You can ask the city for the space’s existing CO; the Certificate of Occupancy page gives the email address, and the request needs the address and the unit number.
Compare the use on that CO with yours. If they differ, you may need the city’s change of use process to get an updated CO for your planned use. That process may include a site plan exemption and a building plan review.
What was approved there before?
Approved plan sets can be found in the public search of the AB+C portal by address or plan review number, and downloaded. They show you, and whoever draws your plans, what the city approved for the space.
What will the landlord need to sign?
Some approvals need the property owner. A site plan exemption request includes a letter from the property owner authorizing the applicant to file with the city. Under the state accessibility law, the building’s owner is responsible for the accessibility inspection, as explained below. Settle in the lease who handles each.
Sources: Zoning Verification; Certificate of Occupancy; Small Business Permitting; Building Inspections; Site Plans, Exemptions, and Corrections (City of Austin); Texas Government Code, chapter 469.
Site plan, correction, or exemption
Before you apply for the building permit, the city needs one of three approvals for the site: a site plan, a site plan correction, or a site plan exemption. The commercial application asks for a copy.
A site plan is a detailed drawing of the improvements and construction on a lot: buildings, parking, driveways, landscaping, and utilities. The city requires one for any site work on a non-residential site, or for a change of zoning use, unless the project qualifies for an exemption. If the city approves a request for concurrent review, a site plan can be reviewed alongside the building application, but the building application cannot be approved before the site plan is.
A site plan exemption is a small-scale development or zoning compliance review for work that meets the exemption criteria in the Land Development Code. It can cover a change of use. It is not a building permit, but a building permit cannot be approved without it. The request goes in through the city’s web form with a drawing of the work reasonably to scale, the applicant’s AB+C account ID, and the property owner’s authorization letter. Up to 10 city disciplines may review it, and it comes back approved or denied; a denied request can be revised and resubmitted.
A site plan correction is a minor change to an approved site plan while the site is actively under construction.
If the project includes site work, check for trees on and next to the lot first. Our guide to Austin’s tree rules explains which trees the city regulates on commercial property.
Sources: Commercial Plan Review; Site Plans, Exemptions, and Corrections; Commercial Building Permit Application (PDF) (City of Austin).
The commercial building permit
Inside the city, you need a building permit to build, enlarge, remodel, repair, convert, move, or tear down a building or structure, unless the work is exempt. Commercial plans are reviewed against the 2024 International Building Code and the city’s local amendments.
The exempt list for commercial work includes painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work, and movable fixtures, cases, racks, counters, and partitions up to 5 feet 9 inches tall. Exempt work still has to meet the codes.
Three review paths
The city sorts commercial applications by size and complexity, and a small, simple finish-out can qualify for a faster review.
| Path | What qualifies | City target |
|---|---|---|
| Quick Turnaround | An interior remodel that adds no square footage, or a tenant finish-out inside an existing building, of 5,000 square feet or less, in an office or retail space (medical, dental, veterinary, and other specialized care excluded). No hazardous materials, no major structural changes, no complex system upgrades such as a large new electrical or gas service, and no septic system. Not in the Wildland-Urban Interface or the floodplain. | 1 business day |
| Small Project | An interior remodel or tenant finish-out under 10,000 square feet, change of use included. | 5 business days |
| Remodel | Work too large or too complex for the two paths above, reviewed by its total square footage. | 10 business days up to 25,000 square feet; 20 above |
These are the city’s targets for its own review, and a remodel’s third review cycle has its own target of 7 business days. A Quick Turnaround permit is limited to one application per submission and cannot be revised; a change means a new application. The city’s page lists every limit.
What the application asks for
The commercial application asks for the current use and the proposed use, the total project square footage, and documents that include these:
- A copy of the approved site plan, site plan correction, or site plan exemption.
- The architectural plans, including a key floor plan.
- Confirmation of the state accessibility registration. The form exempts commercial projects under $50,000.
- The Floodplain Supplemental Form, if the space is in the floodplain and the scope did not get a new site plan determination.
- A Statement of Special Inspections.
- Mechanical, electrical, and plumbing plans, sealed by a professional engineer when the work is in a building or part of one over 5,000 square feet.
- For a restaurant, the Austin Public Health application and health plans.
- For a new electrical service where Austin Energy is the provider, or a change to an existing Austin Energy service, an Electrical Services Planning Application.
The form lists the rest. To meet with plan reviewers before you apply, ask for a Preliminary Plan Review, a paid meeting. The city requires one for any pre-application consultation that needs more than 20 minutes or two or more major code disciplines.
Applying and answering comments
The applicant needs an AB+C account and submits through the city’s web form. Once intake accepts the project, the city sends an invoice, and review starts when it is paid. Reviewers take plans in the order received.
When the review is done, the city sends an approval or a Master Comment Report, which the owner or the owner’s agent has to address. An update includes the report, a written response to each comment, and the complete updated plan set, not only the changed sheets. If anything is still out of compliance after a review, the update process may need to be repeated.
On our commercial jobs, you or your architect submits the application and answers the review comments, and we pull the permit as the general contractor once it is approved.
When the last reviewer approves, the city creates the permits and emails that they are pending activation.
Sources: Commercial Plan Review; Work Exempt from Building Permits; Commercial Building Permit Application (PDF) (City of Austin).
The Texas accessibility review
Texas has its own accessibility law, Texas Government Code chapter 469, with a review and an inspection separate from the city’s permit. The Texas Department of Licensing and Regulation runs it, and the standard it enforces is the 2012 Texas Accessibility Standards (TAS).
Which buildings it covers
For a private business, the law covers buildings that the federal Americans with Disabilities Act defines as a public accommodation or a commercial facility. Public accommodations include restaurants, stores, banks, gyms, and the offices of service providers such as accountants, lawyers, and health care providers. A commercial facility is one intended for nonresidential use whose operations affect commerce.
The threshold and the filing deadline
When the work is on a covered building and the estimated construction cost is at least $50,000, the plans have to be submitted to the state for review and approval. A project below that still has to meet TAS; it is not required to be submitted for registration and review.
The architect, interior designer, landscape architect, or engineer with overall responsibility for the design submits the plans by the 20th day after issuing them, not counting Saturdays, Sundays, or legal holidays, and again after each later issue.
The building’s owner may not let a permit application be filed, or construction start, before the plans are submitted, and gives the city proof of the submission with the permit application. The city may not accept the application until it verifies the project’s accessibility registration. Substantial changes to approved plans go back for review.
Review and inspection
The plan review and the inspection are done by the state, an entity under contract with it, or a Registered Accessibility Specialist (RAS), a person the state has registered for the work. The state’s FAQ says a registered project must have its plan review before the inspection.
The building’s owner is responsible for having the building inspected for TAS compliance by the first anniversary of the date construction is completed. The state’s project records must name, as the owner, the entity that holds title to the property, matching the county appraisal district’s records. If you lease the space, that owner is not you, so agree in the lease who arranges and pays for the review and the inspection.
Tenant spaces and the path of travel
TAS calls an area containing a major activity the building is intended for a primary function area. Its examples are a bank’s lobby and its teller areas; entrances, corridors, and restrooms are not primary function areas.
When work affects, or could affect, the use of or access to a primary function area, TAS 202.4 requires that the path of travel to it be made accessible to the maximum extent feasible, including the parking, restrooms, telephones, and drinking fountains that serve it, unless that work would be disproportionate to the overall alteration in cost and scope. The state decides what is feasible and what is disproportionate through its variance procedures.
A tenant’s alterations in areas only the tenant occupies do not, on their own, put a path-of-travel obligation on the landlord for the areas under the landlord’s authority, unless those areas are being altered too. That makes the shared entrance, restrooms, and parking worth asking about before you sign.
A tenant suite in a multi-tenant building, in plan. The heavy outline is the building. Schematic, not to scale.
- Your suite, the altered area (hatched): a primary function area.
- The path of travel to it (dashed): the parking, the route from it, and the entrance.
- The restrooms and the drinking fountain that serve the suite.
- Areas under the landlord’s authority (shaded): here the corridor and the restrooms, which the path of travel runs through.
TAS is not the ADA
TAS is meant to be consistent with the federal 2010 standards for accessible design and is generally the same, except where it notes otherwise. The ADA is a separate federal law: TAS itself says covered entities must also comply with the federal regulations under the ADA, which cover issues TAS does not. The state says its project registration cannot determine compliance with the ADA.
Sources: Texas Government Code, chapter 469; Americans with Disabilities Act definitions, 42 U.S.C. 12181; Accessibility program, Accessibility FAQ, and TAS chapter 1 and chapter 2 (Texas Department of Licensing and Regulation); Commercial Building Permit Application (PDF) (City of Austin).
Trade permits
When the city approves the building application, it creates the building permit and the related trade permits. In Texas, each of these trades requires a license and registration with the state board or department for that trade, and registration with the city’s Building and Trade Contractor Services.
A trade permit cannot be activated until the building permit is. The trade contractor on each mechanical, electrical, or plumbing permit activates and pays for it, does the work, and schedules its inspections. The general contractor on the building permit manages these trade permits, where they apply.
A stand-alone building or trade permit may be issued if the complete scope of work qualifies. Outdoor signage needs its own sign permit, though some signs may be exempt.
Sources: Commercial Plan Review; Building and Trade Contractor Services; Registering as a contractor; Activating a Permit; Sign Permits (City of Austin).
Activation and inspections
An approved permit has to be paid for and activated before work starts. Only a registered general contractor or a homeowner acting as a general contractor can pay for and activate a building permit. In Texas, anyone can be a general contractor, and no state license is required.
The permit is posted on the property’s entrance side, where it can be seen from the street, and a paper copy of the approved plans stays on site for the inspectors.
The city makes the general contractor on the building permit responsible for scheduling the inspections, the final building inspection included, and for obtaining the certificate of occupancy where one applies. Anyone listed on the permit can schedule an inspection, in the AB+C portal or by phone, and the permit holder and the owner-general contractor are responsible for the order. Inspections usually happen 24 hours after they are scheduled, and an inspector’s workload can push one to the next business day or 48 hours. A failed or partial inspection can be scheduled again.
The city’s inspection stages
The city publishes a commercial building inspection flowchart in four stages, below. Your printed permit lists the inspections your project needs and their codes.
-
Pre-construction
A meeting and inspection on site, where the building inspector meets the contractor.
- The inspector confirms the address, the permits, and the project contacts, and checks the plans, the special inspections, any rated assemblies, and the plans examiner’s notes.
- Site checks: portable restrooms, trash receptacles, work in the right-of-way, overhead power lines, landings and accessibility, design standard requirements, and safeguards.
- Trade contractors can call in their inspections only after it passes.
- The address stays posted where it can be seen from the street through construction. Erosion and sediment controls and tree protection go in before construction starts, where the project needs them.
-
Pre-foundation
- Third-party layout and foundation inspections. The contractor gets a letter from the third party for each, and the final letters go to the inspector at the final inspection.
- Every mechanical, electrical, and plumbing rough inspection.
-
Framing and interior
- 605 Wildland-Urban Interface, with Austin Fire, where it applies.
- Third-party framing (trusses and structural framing) and fire stop inspections, each with a letter.
- Insulation, with the energy reports and checklists.
- Wallboard.
-
Final
- One-time inspections by other city departments, where they apply: environmental, landscaping, Austin Fire, Austin Public Health, Austin Water taps and temporary utilities, and on-site sewage facilities.
- Final trade inspections: 305 electrical, 405 mechanical, 521 plumbing, 609 fire, and 111 energy.
- 112 Final building, scheduled after the plumbing, electrical, mechanical, one-time, and fire inspections have passed and every special inspection letter is uploaded to the permit.
-
Certificate of occupancy
When every inspection has passed, the permit is closed out and the CO is issued.
Special inspections are separate. When a project needs them, the permit comes with a field folder that stays on site, and the special inspector or testing agency fills in its log. The city does not perform special inspections.
Sources: Activating a Permit; Registering as a contractor; Commercial Plan Review; Schedule a Building Inspection; Building Inspections; Commercial Building Inspections flowchart (PDF); Building Pre-Construction Inspection Checklist (PDF); Building Final Inspection Checklist (PDF) (City of Austin).
The certificate of occupancy
The city issues the CO after a successful final inspection for new construction or significant renovations. If yours does not arrive, the Certificate of Occupancy page explains how to request it. For a structure no one occupies, such as a shell building, a certificate of compliance may be requested instead.
Do not move in early. Until the CO or a temporary certificate is granted, the only things allowed in the space are those permanently attached or hardwired and shown on the approved plans. Occupying or stocking the space without an approved temporary certificate may result in the temporary utilities being withdrawn and a referral to Code Compliance.
A temporary certificate of occupancy
A temporary certificate of occupancy (TCO) may let you occupy, stock, or furnish the space before the final CO. Its building inspection is either 108 TCO Stocking or 109 TCO Occupancy, and your inspector can tell you which you need.
- Request it through the city’s web form, one request for each building permit. The city adds the TCO fees to the active permits, and they are paid before the TCO inspections can be scheduled.
- Each trade permit has to show Final or pass its own trade TCO inspection, and each one-time inspection the permit lists has to pass or have its TCO inspection approved.
- Then the building TCO inspection, 108 or 109. An approved TCO is issued with a 90-day expiration and posted next to the main entrance. Extending an expired TCO takes a new TCO inspection.
- Finish the work and the remaining final inspections, then pass the 112 Final Building inspection. The CO is issued, if applicable, and the TCO may be removed.
Sources: Certificate of Occupancy; Commercial Building Inspections flowchart (PDF); Building Final Inspection Checklist (PDF); Commercial TCO and Stocking Process flowchart (PDF) (City of Austin).
Fees to plan for
Fees change, so this guide lists no amounts. The city’s commercial fee schedule has its current figures, and the city’s fees are not refundable, so choose the right project type when you apply. The kinds to plan for:
- The site plan exemption invoice, paid before its review starts.
- The plan review invoice, sent once intake accepts the application; review starts when it is paid.
- A fee for each update from the second on. A Quick Turnaround application is charged per review cycle.
- Permit fees, separate from the application fees, paid when the permit is activated.
- A Preliminary Plan Review meeting, billed at each review discipline’s hourly rate, if you ask for one.
- TCO fees, added to the active permits, if you need a temporary certificate.
- The state’s accessibility project fees: a filing fee and review and inspection fees, on its fee schedule.
Sources: Commercial Plan Review; Commercial Building Plan Review and Permit Fees (PDF); Site Plans, Exemptions, and Corrections; Activating a Permit; Certificate of Occupancy (City of Austin); Accessibility project fees (Texas Department of Licensing and Regulation).
Official links
Every page this guide relies on:
- Small Business Permitting: The change of use process, sign permits, and the small business appointment.
- Zoning Verification: Looking up zoning in Property Profile, permitted uses, and the zoning verification letter.
- Property Profile: The city's map of a property's zoning and development regulations.
- Certificate of Occupancy: What a certificate of occupancy is, requesting an existing one, and the temporary certificate.
- Austin Build + Connect (AB+C) Portal: The public search for permits and approved plan sets, applications, fees, and inspections.
- Site Plans, Exemptions, and Corrections: When a site plan is required, the site plan exemption and what it needs, and site plan corrections.
- Commercial Plan Review: The code edition, the review paths and their limits, the city’s review targets, the application steps, and updates.
- Commercial Building Permit Application (PDF): The documents the city asks for with a commercial building permit application.
- Work Exempt from Building Permits: Commercial work that needs no building permit.
- Texas Government Code, chapter 469: Which buildings the state accessibility law covers, the plan review threshold, filing before the permit application, and the inspection after completion.
- Americans with Disabilities Act definitions, 42 U.S.C. 12181: What counts as a public accommodation and a commercial facility.
- Accessibility program, Texas Department of Licensing and Regulation: The state program page, and who the state’s project records must name as the owner.
- Accessibility FAQ, Texas Department of Licensing and Regulation: Projects under the threshold, when the plan review happens, tenant-funded work, and the ADA.
- 2012 Texas Accessibility Standards, chapter 1: Section 101: how the state standards relate to the federal ADA.
- 2012 Texas Accessibility Standards, chapter 2: Section 202.4: the path of travel to an altered area, and the tenant exception.
- Accessibility project fees, Texas Department of Licensing and Regulation: The state’s project filing, review, and inspection fees.
- Activating a Permit: Who can activate a building permit, trade permits after it, and posting the permit.
- Registering as a contractor: What the general contractor and the trade contractors are responsible for, and what each trade needs from the state.
- Building and Trade Contractor Services: Activating the building and trade permits, and stand-alone trade permits.
- Sign Permits: The permit for outdoor signage.
- Building Inspections: The approved plans on site, special inspections, one-time inspections, and the commercial flowcharts and checklists.
- Schedule a Building Inspection: Who can schedule an inspection, the order of inspections, and the inspections listed on the permit.
- Commercial Building Inspections flowchart (PDF): The four stages of commercial building inspections, from pre-construction to the final and the CO.
- Building Pre-Construction Inspection Checklist (PDF): The pre-construction inspection comes before any plumbing, electrical, or mechanical inspection.
- Building Final Inspection Checklist (PDF): What has to pass before the final building inspection, and what may be in the space before a CO.
- Commercial TCO and Stocking Process flowchart (PDF): Requesting a temporary certificate of occupancy, its inspections and expiration, and the final CO.
- Commercial Building Plan Review and Permit Fees (PDF): The city’s commercial fee schedule, linked from the Commercial Plan Review page.