Guide

Austin’s tree rules

A large tree on your lot, or close to it on the lot next door, can decide where a house, an addition, or a parking area goes. This guide explains which trees the City of Austin regulates, what counts as affecting one, and how the tree review and the tree inspections fit into your project.

Each rule here links to the city’s own page. City staff decide what a project needs, so confirm the details for yours with the City Arborist team.

Will a tree affect your project?

Three questions settle it.

  1. Is the lot inside Austin’s jurisdiction? The city’s tree ordinance applies inside the city limits and in its limited-purpose areas. It does not apply in the extraterritorial jurisdiction (ETJ).
  2. Is there a regulated tree on the lot, or next door with its root zone reaching onto the lot? On a home lot, that is a tree 19 inches or more in diameter. On commercial and multifamily property, it is 8 inches or more.
  3. Will the work remove the tree, prune a quarter or more of its canopy, or disturb its critical root zone? If so, the work needs a tree permit.

If the first two answers are yes and a home project needs a building permit, show the regulated trees on the plans and answer yes to the application’s question about protected trees, even if the work will not touch them: that is how the city assigns a tree reviewer. Keep their root zones protected while the work goes on, because soil packed down by equipment counts as an impact. If the third answer is also yes, plan the design around the root zones.

Which trees are regulated

Any tree 19 inches or more in diameter is a protected tree, whatever the species. On residential property, trees under 19 inches are not regulated.

A heritage tree is one of these species at 24 inches or more in diameter:

  • Texas ash
  • Bald cypress
  • American elm
  • Cedar elm
  • Texas madrone
  • Bigtooth maple
  • Any oak
  • Pecan
  • Arizona walnut
  • Eastern black walnut

Removing a heritage tree, or affecting one beyond what the code allows, takes a variance. The heritage section covers how that works.

On commercial and multifamily property, and on development projects that need a site plan, the line is lower: every tree 8 inches or more in diameter is regulated.

A tree next door counts too. Where a neighbor’s tree has a critical root zone that reaches onto your lot, the tree review includes it, and the protection rules apply to it during construction.

How to measure a tree

Diameter is measured 4.5 feet above the ground. Wrap a flexible tape around the trunk at that height and divide the distance around by 3.14. A trunk 60 inches around is 19 inches across.

  • On a slope, measure 4.5 feet up from the high side.
  • If the trunk swells at that height, measure above or below the swelling.
  • If the tree leans, measure 4.5 feet up, in the center area of the leaning trunk.
  • If the tree has more than one stem, measure each stem, then add half of each smaller stem to the largest. In the city’s example, stems of 18 and 16 inches make a 26-inch tree.

Measuring a trunk’s diameter, in elevation. Schematic, not to scale.

  • Measure around the trunk 4.5 feet above the ground and divide by 3.14.
  • On a slope, measure the 4.5 feet from the high side.
  • With more than one stem, add half of each smaller stem to the largest: 18 inches plus half of 16 makes 26.

Sources: City Arborist; Trees on Residential Property; Trees on Commercial and Multifamily Property; Glossary of Terms; Residential Tree Review Checklist (PDF); Tree Protection and Erosion/Sedimentation Controls flowchart (PDF) (City of Austin).

What counts as affecting a tree

On a home lot, you need a tree permit, through a Tree Ordinance Review Application (TORA), to do any of three things to a regulated tree:

  • remove it;
  • prune 25% or more of its canopy;
  • start an activity that may affect it or disturb its critical root zone.

The critical root zone

The critical root zone is a circle around the trunk with a radius of one foot for each inch of diameter. A 20-inch tree has a root zone reaching 20 feet from the trunk, with the half zone at 10 feet and the quarter zone at 5.

Each ring has its own limit:

  • The quarter zone: no impacts at all.
  • The half zone: no cut or fill of more than 4 inches.
  • The full zone: at least half of it stays at natural grade, with natural ground cover.

An impact can be inches underground. Soil packed down by construction equipment counts, and so does a change in grade.

The critical root zone of a 20-inch tree on the lot next door, in plan. Each inch of diameter is one foot of radius. Schematic, not to scale.

  • The quarter zone, 5 feet out: no impacts.
  • The half zone, 10 feet out: no cut or fill of more than 4 inches.
  • The full zone, 20 feet out: at least half of it stays at natural grade, with natural ground cover.
  • The part of the neighbor’s root zone on your lot (hatched) counts in your tree review.

What the root zone means for the design

The root zone limits where the house, the driveway, and the utilities go, so draw the zones on the site plan before the design gets far. The city’s tree review checklist calls out these:

  • The foundation. Leave room for forms, bracing, drainage, and working space when you set the foundation near the half zone.
  • Sidewalks and driveways. Keep them out of the half zone of a protected tree if at all possible. If they cannot avoid it, other designs and construction methods have to be considered, and the city’s criteria manual has a low-impact driveway detail.
  • Utilities. The plans show the existing and proposed utility lines, underground and overhead, and the meter locations.
  • Pool equipment. The equipment and its trenching have to avoid the half zone of protected trees, or air excavation by a certified arborist may be required.

On commercial and multifamily sites, piers with a suspended slab may be allowed in the half zone, case by case and at City Arborist staff’s discretion.

Sources: Trees on Residential Property; Trees on Commercial and Multifamily Property; Glossary of Terms; Residential Tree Review Checklist (PDF); Tree Protection and Erosion/Sedimentation Controls flowchart (PDF) (City of Austin).

The tree review and your permit

On a home that needs a building permit

When a home project with a regulated tree on or next to the lot needs a building permit, the tree review happens at the same time as the building plan review, and the tree permit comes with the building permit. It is one of the review groups a site condition can add, and the permit roadmap shows where it fits in the rest of the process.

On the application, answer yes to the question about protected trees; that is how the city assigns a tree reviewer. A tree review fee is due when the plans go in. If City Arborist staff decide the project does not need a tree review, the city refunds it.

The city’s Residential Tree Review Checklist lists what the plans show. The main items:

  • A plot plan with every protected and heritage tree on the lot, and on neighboring lots where a root zone reaches yours.
  • Each tree’s diameter and exact species: live oak or post oak, not just oak.
  • The quarter, half, and full root zones, drawn to scale, and on the foundation plan too where they overlap the foundation.
  • Trees to keep drawn as solid circles, and trees to remove dashed or called out.
  • A separate tree preservation plan sheet when the work reaches into the root zones of three or more protected or heritage trees.
  • Access routes, material staging, the dumpster and spoils, the portable toilet and concrete washout, utilities, and where the tree protection goes.

To help make an application complete, the city also links sample tree survey plans by AIA Austin, made with its Development Services Department.

A letter from a certified arborist you hire is recommended. It covers how much of the canopy the work needs removed, the construction methods, or the tree’s health. It is required during review when construction is proposed inside the half zone of a protected tree, or when the trees and the work plainly conflict.

Asking to remove a protected tree for the project takes a justification, and an approved removal may require mitigation. If you ask to remove one because of its condition, include a certified arborist’s letter with an ISA risk assessment form.

When no building permit is needed

If everything in the work is on the city’s list of work exempt from building permits, the tree permit is a standalone TORA, filed in the Austin Build + Connect (AB+C) portal. Any conditions, including whether inspections are needed, are written on the permit.

A dead, diseased, or hazardous regulated tree still needs an approved TORA before it comes down. Removing or damaging a regulated tree without approval is a violation.

Talking to the city before you design

If your work affects regulated trees, the property owner or the owner’s agent can ask for a pre-plan submittal consultation: a paid, on-site visit where city staff go over the rules, which trees must be preserved or mitigated, and any variances. The City Arborist team also takes short appointments for general questions.

On commercial and multifamily property

The 8-inch threshold applies, and so do the root zone limits: half of the zone at natural grade, no cut or fill of more than 4 inches in the half zone, and no impacts in the quarter zone. The application depends on the project. The city points you to the Land Use Review Application for your project type, and to an appointment with the City Arborist group to settle which one. If the work will affect heritage trees, a pre-plan submittal consultation is available here too.

For a commercial build-out or tenant finish-out, our guide to commercial build-outs in Austin covers the rest of the approvals, from the site plan to the certificate of occupancy.

Sources: City Arborist; Trees on Residential Property; Residential Plan Review; Residential Tree Review Checklist (PDF); AIA Austin Tree Survey Samples (PDF); Dead, Diseased and Imminent Hazard Trees; Report a Tree Violation; Trees on Commercial and Multifamily Property (City of Austin).

Heritage trees and variances

Removing a heritage tree is prohibited except as the city code provides. Removing one, or affecting one beyond what the code allows, takes a variance.

The tree review checklist says removing a healthy heritage tree goes through an administrative or a commission variance process, with its own fees.

For a heritage tree 30 inches or more in diameter, a proposed variance must go through a public process.

So if a heritage tree stands where you hoped to build, raise it before the design is drawn. A pre-plan submittal consultation is one place to talk through a variance with city staff.

Sources: City Arborist; Residential Tree Review Checklist (PDF); Trees on Residential Property (City of Austin).

Protecting trees during construction

Where a project needs tree protection, it has to be in place before construction starts, and the final tree inspection checks that it is still there at the end. The city’s tree flowchart describes it:

  • Mulch: 8 inches of hardwood mulch across the full root zone.
  • Fence: 5-foot chain-link fencing around the full root zone.
  • Where the work comes closer: fence as much of the root zone as you can. The fence can be pulled back, but not into the half zone.
  • Where fencing is not an option: 2x4 lumber, 6 feet long or larger, strapped upright around the trunk. Confirm with your inspector before using planks instead of fencing.
  • The quarter zone: no impacts.

The portable toilet, the concrete washout, the dumpster, equipment, material staging, and erosion controls stay out of the half zone of a protected tree. If the only way onto the site crosses a root zone, ask your tree inspector about other ways to protect the roots.

The flowchart’s daily compliance list includes keeping the tree protection in place.

Tree protection around a root zone, in plan. Schematic, not to scale.

  • Chain-link fence, 5 feet tall, around the full root zone.
  • Where the house comes inside the root zone, the fence is pulled back, but never into the half zone (the outer dashed circle).
  • 8 inches of hardwood mulch over the full root zone.
  • Where fencing is not an option, 2x4 lumber 6 feet long or larger strapped upright around the trunk, after checking with your inspector.
  • Staging, the dumpster, the portable toilet, and the concrete washout stay out of the half zone. Here they sit outside the root zone altogether.

Sources: Tree Protection and Erosion/Sedimentation Controls flowchart (PDF); Residential Inspections Process flowchart (PDF); Residential Tree Review Checklist (PDF) (City of Austin).

Tree inspections, in order

On a residential project with a tree review, the city’s Tree Protection and Erosion/Sedimentation Controls flowchart sets the order. Two tree inspections are booked for you when you schedule a building inspection. You schedule the pre-pour and final tree inspections like any inspection, in the AB+C portal or by phone.

  1. Erosion and sediment controls

    Before any work on the site

    The controls go in before any work takes place, and a pre-construction erosion and sedimentation control inspection comes first.

  2. Pre-construction tree inspection

    Booked when you schedule 101 Layout

    Tree protection fencing and mulch in place, the building layout staked and stringlined, and form boards in place where the project uses them.

    Additions and remodels book 101 Layout to get this inspection too. For work with no framing, such as a pool or some interior work, the interim tree inspection is set up at this point.

  3. 621 Pre-pour tree inspection

    After excavation, before the reinforcing steel and poly plastic go in

    Tree protection in place and maintained, the perimeter grade beam and excavation done, batter boards and form boards in place where used, and the rough plumbing trench where there is one.

  4. Interim tree inspection

    Booked when you schedule 103 Framing

    The full tree protection fencing and mulch in place, and no impacts to the roots or the canopy.

  5. 620 Final tree inspection

    After the later building inspections, such as insulation and wallboard

    Before you schedule it: arborist receipts sent to your tree inspector, any mitigation trees planted, the first treatment of the tree care plan done, heavy equipment, staging, and hardscaping cleared and finish grading done, tree protection still in place, and any reinspection fees paid.

    The final environmental inspection is scheduled at the same time, and the two happen together.

  6. 112 Final building inspection

    Once the 602 environmental inspection passes

    The one-time 602 environmental inspection has to pass before the final building inspection can go ahead. It needs the site and the area around it free of sediment, and all trash and debris contained.

Before a temporary certificate of occupancy, contact the building, tree, and environmental inspectors about anything more they need. The permit roadmap shows the full building inspection sequence these fit into.

On a commercial site, schedule tree and environmental inspections with your assigned inspector. The city’s Commercial Environmental Territories Map shows who that is.

Sources: Tree Protection and Erosion/Sedimentation Controls flowchart (PDF); Residential Inspections Process flowchart (PDF); Trees on Residential Property; Environmental Inspections (City of Austin).

Where the city’s tree rules do not apply

The tree ordinance does not apply in Austin’s extraterritorial jurisdiction (ETJ), the unincorporated land within five miles of the city limits that is not in another city or its ETJ. It does apply in limited-purpose areas, where limited-purpose annexation extends the city’s land development and environmental rules.

Check where your lot sits on the city’s Jurisdictions Web Map. The permit roadmap explains what the city does regulate in the ETJ.

On a home lot, a tree under 19 inches needs no tree permit, though the project may still need other permits.

Sources: City Arborist; Jurisdictional Matters; Jurisdictions Web Map; Trees on Residential Property (City of Austin).

Tree fees

The city’s fees change, so we do not list amounts here. Its Tree Review and Inspection Fees schedule has the current ones, including:

  • the residential tree plan review, and an update fee;
  • tree inspections, the pre-pour tree inspection, and reinspections;
  • a tree review with no building permit;
  • the pre-development consultation;
  • heritage tree variances, administrative and commission.

The schedule waives the fees for dead, diseased, or imminent hazard trees.

Outside the city’s fees, plan for the arborist’s letter where the review calls for one, and for any mitigation.

Sources: Tree Review and Inspection Fees (PDF); Residential Tree Review Checklist (PDF) (City of Austin).

Plan around your trees with us

Email or call with the address and what you want to build.

We are the general contractor for custom homes and remodels and for commercial build-outs.

On a home we build, we can prepare and submit the permit application, answer the city’s review comments, and pull the permit as the general contractor. Or, if you or your architect submits the application and answers the review comments, we pull the permit as the general contractor. The permit roadmap explains how we can help with your permit.

AGC Design is registered with the City of Austin as a general contractor.