Building an ADU in Austin

What it takes to add a guest house, a garage conversion, or a second home to a lot inside Austin’s city limits: what the city counts as a unit, how many your lot can have, and the permit path.

Each rule here links to the official page it comes from. Rules change, and city staff decide what a project needs, so confirm the details for your lot with Austin Development Services. Its residential zoning appointments take ADU questions.

How we can help with your ADU

We build ADUs: guest houses and garage conversions.

On a home we build, we can take the whole permit on: we prepare and submit the application, answer the city’s review comments, and pull the permit as the general contractor.

Or, if you or your architect submits the application and answers the review comments, we pull the permit as the general contractor.

AGC Design is registered with the City of Austin as a general contractor.

What the city counts as an ADU

An ADU is a separate dwelling unit on the same lot as a house. A space is a dwelling unit when it has all three of these:

  • habitable space;
  • a full bathroom: a toilet, a sink, and a shower or a tub;
  • permanent cooking: a stove installed in place, such as one on a 240-volt outlet, and a sink or a dishwasher outside the bathroom.

A microwave or a hot plate is not permanent cooking. Once a space has all three, every rule for a dwelling unit applies to it, including zoning, utility meters, its address, and occupancy.

The city also looks at how independently two spaces could work. An extra sink outside a bathroom is one of the signs it weighs. If your plan has only some of the three, book a residential zoning appointment to talk through what the lot allows.

What makes a space a dwelling unit, in plan. Schematic, not to scale.

  • Habitable space for living and sleeping.
  • A full bathroom: a toilet, a sink, and a shower or a tub.
  • Permanent cooking: a stove installed in place. A microwave or a hot plate does not count.
  • A sink or a dishwasher outside the bathroom.

Guest house, garage apartment, or duplex?

The code no longer has separate categories for guest houses or accessory apartments, and neither unit on the lot counts as the secondary one. The HOME rules ended both. What matters is whether the units share a building:

  • A house and a unit in its own building, such as a backyard cottage or a converted detached garage, are a two-unit residential use.
  • Two units in one building, such as a house with a converted attached garage, are a duplex.

Both follow the same rules, described below.

Sources: Additional Dwelling Units; Code Interpretation CI2026-0003, Dwelling Unit Components (PDF); HOME Amendments; Code Interpretation CI2026-0002, Duplex, Two-Unit, and Three-Unit Site Development Standards (PDF); Ordinance No. 20231207-001, HOME Phase 1 (PDF) (City of Austin).

The HOME rules, Phase 1 and Phase 2

Austin’s HOME amendments rewrote the rules for adding homes to a lot in single-family zoning. They came in two phases, and the dates matter: articles, plans, and approvals from before them describe rules that are gone.

Phase 1: up to three units

Phase 1 allows up to three housing units, tiny homes included, on a lot zoned SF-1, SF-2, or SF-3. It also set new rules for two units on a lot and removed the limit on how many unrelated adults can live in a home. The city has accepted applications under it since February 5, 2024.

Phase 1 applies only to duplexes and two- and three-unit uses. A lot with one house is still reviewed under the older single-family rules, Subchapter F included.

Phase 2: one home on a small lot

Phase 2 allows one home on a lot of at least 1,800 and under 5,750 square feet. The city began accepting applications under it on August 16, 2024, and citywide on November 16, 2024, once properties in the Wildland-Urban Interface and in areas the city’s Uprooted report designated were included. A small lot can have only one dwelling unit, so Phase 2 never adds an ADU. Unless a lot is already under 5,750 square feet, using it means a subdivision to split the lot. The city’s HOME Phase 2 Guide checks whether a lot qualifies.

Changes under way

The City Council has started work on amendments to the two-unit, three-unit, and small lot rules. Check the HOME Amendments page before your design is final.

Sources: HOME Amendments; Ordinance No. 20231207-001, HOME Phase 1 (PDF); HOME Phase 2 Guide; Code Interpretation CI2026-0002, Duplex, Two-Unit, and Three-Unit Site Development Standards (PDF) (City of Austin).

How many units can your lot have?

Three things decide it: the zoning district, the lot size, and anything layered on top of the zoning. Look up your zoning on Property Profile first.

Dwelling units the HOME rules allow on a home lot
Your lot Dwelling units allowed
Zoned SF-1, SF-2, or SF-3, and 5,750 square feet or more Up to three dwelling units, the house included, attached or detached in any combination
Zoned SF-1, SF-2, or SF-3, at least 1,800 and under 5,750 square feet One dwelling unit, under the small lot rules, so no ADU
Any other zoning district Its own rules; ask the city’s residential zoning staff

A lot under 5,750 square feet cannot add a unit through the small lot rules or through a neighborhood plan’s small lot amnesty. Both are for a single home.

What can change the answer

  • Overlays. A neighborhood conservation combining district, a neighborhood plan, a conditional overlay, or another combining district can apply on top of the zoning. Where one conflicts with the HOME rules, the overlay controls.
  • An older option in some neighborhood plans. Some neighborhood plans still allow a secondary apartment, with its own size and placement limits. It cannot be combined with the HOME rules for two or three units.
  • Deed restrictions and HOA rules. These can limit a lot that the zoning opens to more units. The city’s review does not cover them, and checking them is your job. The permit roadmap explains how to check deed restrictions and HOA rules.

Sources: Additional Dwelling Units; HOME Amendments; Code Interpretation CI2026-0002, Duplex, Two-Unit, and Three-Unit Site Development Standards (PDF); Residential New Construction and Addition Permit Application (PDF); Property Profile (City of Austin).

Size and placement

Once a lot has two or three units, the HOME rules set how much can be built and where. These are the limits that shape a backyard unit or a conversion.

Coverage

Buildings can cover at most 40% of the lot, and impervious cover, meaning roofs, paving, walkways, and driveways, at most 45%. Garages and carports count toward both.

Floor area inside the Subchapter F boundary

Inside the Subchapter F boundary, the code caps floor area for the whole site and for each unit, and on a three-unit lot for any two units together. Every enclosed space with more than six feet of clear height counts, garages, lofts, and storage included. A carport or a porch that is not enclosed does not.

The city’s application works these caps out as floor-to-area ratios, floor area divided by lot area, for each building, each pair of buildings, and the site. Pin the numbers down for your lot before the design gets far. If you keep part of an older house, the preservation bonus can leave the preserved square footage out of the count.

Height and setbacks

Height follows the base zoning district. The 32-foot Subchapter F limit is for single-family use, a lot with one house, not two or three units.

Two- and three-unit lots have a 15-foot front setback. At the rear, the setback is the zoning district’s, cut to 5 feet where the rear lot line meets an alley or a lot with a use allowed in multifamily zoning. The side setbacks are the zoning district’s.

Space between the units

Zoning sets no minimum distance between units. The building code still does: its fire separation rules govern walls, eaves, windows, and doors close to another unit or a property line. Two units joined by a breezeway need fire separation where they connect.

The rest of the site

  • A two- or three-unit site needs at least one street-facing entrance: a front door, or a front porch leading to it, facing the street. A house whose front stays unchanged is exempt, but if the new unit can be seen from the street, the site needs one.
  • No part of a roof can overhang a public utility or drainage easement.

A home lot with a house and a new rear unit, in plan. The heavy outline is the property line, and the dashed line marks the setbacks. Schematic, not to scale.

  • The rear setback: the zoning district’s, or 5 feet where the rear lot line meets an alley, as here.
  • No zoning distance between the units. The building code’s fire separation rules govern the walls, eaves, and openings that face each other.
  • A street-facing entrance, here the house’s front porch.
  • At most one water meter for each unit, and the same for electric and gas. Meters and cleanouts cannot sit under a driveway or a sidewalk.
  • A power line. Austin Energy checks the plans for clearance from lines, poles, and electric easements.

Tiny homes

A tiny home, 400 square feet or less not counting a loft, can be one of the units. It sits on a permanent foundation, has its own address, and connects to water, sewer, and electric service for good. A tiny home on wheels counts as a recreational vehicle and is not allowed as a home on a residential lot. The application adds the city’s tiny house modification form.

Sources: HOME Amendments; Code Interpretation CI2026-0002, Duplex, Two-Unit, and Three-Unit Site Development Standards (PDF); Ordinance No. 20231207-001, HOME Phase 1 (PDF); Additional Dwelling Units; Policy Memo PM2024-0003, Residential Breezeways Between Dwelling Units (PDF); Residential New Construction and Addition Permit Application (PDF); Code Interpretation CI2026-0003, Dwelling Unit Components (PDF); Building Under HOME: Tiny Homes (PDF) (City of Austin); Austin Energy Residential Review.

Parking

The city requires no off-street parking for any use, so an ADU does not need a parking space.

If you add parking anyway, the two- and three-unit rules decide where it goes:

  • Impervious cover in the front yard is capped at 40%.
  • No more than four parking spaces can be in the front yard, or on a corner lot, in the front and side street yards together.
  • A garage or carport for any unit cannot sit between the street and the front wall of the house closest to it. A front-facing one less than 20 feet behind that wall can be no wider than the house’s front.

For a duplex or a house and one other unit, some neighborhood plans have their own garage placement rules, which apply instead. A three-unit lot follows the rules above wherever it is.

Sources: Ordinance No. 20231102-028, minimum parking (PDF); Ordinance No. 20231207-001, HOME Phase 1 (PDF); Code Interpretation CI2026-0001, Parking Structure (Garage) Placement (PDF) (City of Austin).

Water, wastewater, and electric service

Austin Water checks service first

Before the building permit application goes in, Austin Water verifies that the site can get water and wastewater service, and flags early any service that has to be moved, added, or upgraded, with its costs and lead times. Building a new home, a garage apartment, or a secondary structure needs this Water and Wastewater Service Plan Verification (WWWSPV), and so does a remodel that adds a unit, such as turning a house into a duplex.

You apply in the Austin Build + Connect (AB+C) portal with a plot plan showing the existing water meter and wastewater cleanout, the half critical root zones of protected trees, and what you plan to build. Austin Water returns a determination letter and a stamped plot plan, and both go in with the permit application.

  • If the letter calls for a utility plan, Austin Water’s tap plan review has to approve it before you can buy the water meter.
  • Changing the number of units, bathrooms, or meters later takes a new verification.
  • Each dwelling unit can have at most one water meter, one electric meter, and one gas meter. Water services, meters, and wastewater cleanouts cannot sit under a driveway or a sidewalk, and private plumbing lines cannot cross a lot line.
  • On a lot with a septic system, adding a unit adds conditioned space, which triggers an on-site sewage facility review with Austin Water.

Electric service

Property Profile shows whether Austin Energy serves your lot. If it does, plan for three things.

  1. An address for each unit that will have its own meter. Austin Energy warns that adding an address late in the process may delay getting power, and the city wants the new unit’s address before the permit application anyway.
  2. An Electric Service Planning Application for each address with a meter. It tells Austin Energy the load the unit needs, and the electric permit depends on it.
  3. Clearance from power lines. During plan review, Austin Energy checks the plot plan for distance from poles, overhead and underground lines, transformers, and electric easements, so all of them have to be on it.

Where the project needs a new water meter, Austin Water’s meter, tap, inspection, and impact fees come on top of the city’s permit fees. The Utility Permitting Office page has the current amounts.

Sources: Water and Wastewater Service Plan Verification instructions (PDF); WWWSPV Application Reference Guide (PDF); Austin Water Utility Permitting Office; Code Interpretation CI2026-0003, Dwelling Unit Components (PDF); Residential New Construction and Addition Permit Application (PDF); Residential Plan Review; Additional Dwelling Units (City of Austin); Apply for Electric Service (Austin Energy); Electric Service Planning Application (Austin Energy); Austin Energy Residential Review.

The permit for a new unit or a garage conversion

The city permits a new ADU as new construction, whether it is a new building or a converted garage. Both go through the Residential New Construction and Addition application. The garage conversion application looks like the right form for a conversion, but it cannot create a dwelling unit or change the building’s footprint or height.

  1. Confirm the lot can take a unit: the zoning, the lot size, any overlay, and any deed restrictions.
  2. Request an address for the new unit from Address Management Services. The city wants it before the application goes in.
  3. Get Austin Water’s determination letter and stamped plot plan through the service plan verification described above.
  4. Apply through the New Construction or Addition web form, with the application, the plans, and for a tiny home, the city’s tiny house modification form.
  5. Pay the plan review invoice and answer the review comments until every review group approves the plans.
  6. Pay for and activate the permits. Construction and inspections can start once they are active.
  7. Pass the final building inspection. The inspector then issues the new unit’s certificate of occupancy.

A new unit with habitable space on the first floor also needs a visitability plan or a waiver. The permit roadmap covers what goes in the application, plan review, the inspections, and the fees in detail.

Building a new unit

The application asks whether a sidewalk is required. The city’s form says one is installed with new construction of a single-family, two-unit, three-unit, or duplex structure, and a required sidewalk adds a transportation review to the plan review.

Converting a garage

  • The garage has to become a full dwelling unit, with habitable space, a full bathroom, and permanent cooking.
  • An attached garage turned into a unit makes the house a duplex, and the two units need fire separation between them.
  • If the garage sits inside a setback, the application asks about it, and the code has its own rules for structures that do not meet today’s setbacks. Raise it before the design starts.

Sources: Additional Dwelling Units; Residential New Construction and Addition Permit Application (PDF); Garage Conversion and Carport/Porch Enclosure Permit Application (PDF); Residential Plan Review; Address Management Services; Water and Wastewater Service Plan Verification instructions (PDF); Code Interpretation CI2026-0003, Dwelling Unit Components (PDF); HOME Amendments (City of Austin).

Trees

A large tree can decide where a backyard unit goes. A tree 19 inches or more in diameter, on your lot or next to it, adds a tree review to the permit. Cut and fill inside its half critical root zone is limited to 4 inches, which a foundation cannot meet, and Austin Water’s plot plan shows the half root zones too.

Our guide to Austin’s tree rules explains which trees are regulated, how the root zone works, and what the tree review asks for.

Sources: Residential Plan Review; Residential New Construction and Addition Permit Application (PDF); Water and Wastewater Service Plan Verification instructions (PDF) (City of Austin).

Renting the unit short term

Since October 1, 2025, a short-term rental, a stay of less than 30 consecutive days, is allowed with any residential use, an ADU included, as long as it has an operator’s license from the city, one for each rental. On a site with three or fewer housing units, one person can operate up to two.

The same change repealed the old limit of 30 days a year as a short-term rental for a newer ADU. The city’s ADU page still describes that limit and a certificate of occupancy requirement; its Short-Term Rentals page has the current rules.

Sources: Ordinance No. 20250227-039, short-term rental use (PDF); Ordinance No. 20250911-012, short-term rental operators (PDF); Short-Term Rentals; Additional Dwelling Units (City of Austin).

Outside the city limits

In Austin’s extraterritorial jurisdiction (ETJ), the unincorporated land within five miles of the city limits that is not in another city or its ETJ, the city does not zone land or regulate how it is used. The HOME rules and the unit counts in this guide do not apply there. The city still enforces environmental rules and approves subdivision plans in the ETJ, so ask both the city and the county which approvals your project needs. Check where your lot sits on the Jurisdictions Web Map.

Sources: Jurisdictional Matters; Jurisdictions Web Map (City of Austin).