The Austin residential permit roadmap
What it takes to permit a custom home, an addition, an ADU, or a remodel inside Austin’s city limits, from the first zoning check to the certificate of occupancy.
Each rule here links to the city’s own page. Rules and forms change, and city staff decide what a project needs, so confirm the details for yours with Austin Development Services.
How we can help with your permit
On a home we build, we can take the whole permit on: we prepare and submit the application, answer the city’s review comments, and pull the permit as the general contractor.
Or, if you or your architect submits the application and answers the review comments, we pull the permit as the general contractor.
AGC Design is registered with the City of Austin as a general contractor.
Do you need a permit?
Inside the city, you need a building permit to build, add on to, remodel, repair, move, or tear down a building or other structure, unless the work is on the city’s exempt list.
That list covers smaller work on a house, duplex, or townhouse of up to three stories:
- Finish work: paint, wallpaper, tile, carpet, cabinets, countertops, and the like.
- A detached one-story shed or similar building of up to 200 square feet and 15 feet tall, with no plumbing, that is not a dwelling.
- A deck of up to 200 square feet, no more than 30 inches off the ground at any point, that is not attached to the house or used as a way out of it.
- A fence up to 7 feet high, or a retaining wall up to 4 feet high with no added load above it.
- A sidewalk, driveway, or other flatwork outside the public right-of-way.
- Replacement doors of the same size that open the same way, and a new roof covering that leaves the roof structure alone.
Three exceptions catch people out:
- In a flood hazard area, the shed, deck, fence, and retaining wall exemptions do not apply.
- In the Wildland-Urban Interface, replacing half or more of the roofing needs a permit.
- A new or replacement shower, tub, or tub and shower combination is not exempt.
Exempt work still has to meet the building codes. To check a specific project, the city’s Do I Need a Permit? questionnaire takes a few minutes.
Sources: Homeowner's Permit; Work Exempt from Building Permits; Do I Need a Permit? (City of Austin).
City limits, ETJ, or county?
Who regulates the work depends on where the lot sits, so find that out first on the city’s Jurisdictions Web Map.
- Inside the city limits, the city’s zoning and its residential permit process apply. That is what this guide covers.
- In Austin’s extraterritorial jurisdiction (ETJ), the unincorporated land within five miles of the city limit that is not in another city or its ETJ, the city does not zone or regulate land use. It still enforces environmental rules and approves subdivision plans. The ETJ reaches into Travis, Williamson, Hays, and Bastrop counties, so ask both the city and the county which approvals your project needs.
- Outside the city limits in Travis County, the county issues its own permit for a single-family home. Get its current requirements from the county.
Sources: Jurisdictional Matters and Jurisdictions Web Map (City of Austin); Travis County single-family home permit (Travis County).
What can you build on your lot?
Zoning decides what fits, so it comes first. Property Profile shows a property’s zoning district, any overlays, and whether it is inside the Subchapter F boundary. The zoning review applies your district’s rules from Chapter 25-2 of the Land Development Code, including the setbacks: how close to each property line you can build.
Up to three units (HOME Phase 1)
The city’s HOME rules allow up to three housing units, tiny homes included, on a lot zoned SF-1, SF-2, or SF-3. With a duplex or two or three units, buildings can cover at most 40% of the lot and impervious cover at most 45%, and garages and carports count toward both.
One home on a small lot (HOME Phase 2)
Phase 2 allows one home on a lot of at least 1,800 square feet and under 5,750 square feet, the standard minimum lot size. Unless your lot is already under 5,750 square feet, using the smaller size means a subdivision application to split it. The city’s HOME Phase 2 Guide checks whether a property qualifies.
Subchapter F still governs a single-family home
Subchapter F, often called the McMansion rules, limits a home’s height, floor area, and bulk. The three-unit rules apply only to duplexes and two- and three-unit uses, so a single-family home is still reviewed under Subchapter F, 32-foot height limit included.
Inside the boundary, all enclosed space counts toward floor area. Garages, lofts, and mezzanines count; carports and porches, which are not enclosed, do not. The limit for your lot depends on the use and the lot itself, so pin it down before the design gets far. The city’s residential zoning appointments are one place to ask.
ADUs
Adding a unit takes SF-1, SF-2, or SF-3 zoning and a lot of at least 5,750 square feet. Our guide to building an ADU in Austin covers the rest: what counts as a unit, size and placement, parking, utilities, and the permit for a new unit or a garage conversion.
Sources: Property Profile; HOME Amendments; HOME Phase 2 Guide; Additional Dwelling Units; Residential Plan Review (City of Austin).
Site conditions that add a review
Every new home, addition, or remodel gets a zoning review, and new structures and structural changes get a building code review. What is on and around the lot can add more. A large tree or a nearby creek can limit where the house goes, so look for them before the design starts.
| If the property or project has | The city adds |
|---|---|
| A tree 19 inches or more in diameter on or next to the lot | Tree review |
| A driveway approach in the right-of-way that is added, moved, removed, or repaired, or a required sidewalk | Transportation review |
| A new water or wastewater tap | Austin Water utility tap |
| A septic system, where conditioned space, bedrooms, or developed footprint is added | On-site sewage facility (OSSF) review |
| More than 3,600 square feet under roof (attached porches, decks, and garages count), a hazardous pipeline within 200 feet, an NFPA 13D sprinkler system, or a lot in the Wildland-Urban Interface | Fire review |
| A property in the 100-year floodplain or within 100 feet of its boundary | Floodplain review |
| A property within 100 feet of the centerline of a creek or stream bed | Erosion hazard zone review |
| A structure 45 years old or older whose exterior is changed or demolished, or a historic landmark or historic district | Historic review |
| A tract not platted in a recorded subdivision, or not a legal lot | Subdivision application or land status determination |
| A storm inlet within 10 feet of a driveway curb cut | Grading and drainage review |
A lot near a creek, in plan. The heavy outline is the property line. Schematic, not to scale.
- Setback lines: how close the house can come to each property line.
- The critical root zone of a tree 19 inches or more in diameter. The inner quarter (darkest) stays undisturbed, cut or fill in the inner half is limited to 4 inches, and at least half of the whole zone stays undisturbed.
- 100 feet from the creek centerline. A property within that line gets an erosion hazard zone review.
- 100 feet beyond the edge of the 100-year floodplain (hatched). A property inside the floodplain or within that line gets a floodplain review.
Large trees
On a residential lot, trees 19 inches or more in diameter, measured 4.5 feet above the ground, are regulated; smaller ones are not. Removing a regulated tree, pruning a quarter or more of its canopy, or working inside its critical root zone needs a tree review, through the Tree Ordinance Review Application. In many cases that is part of the building permit application.
Inside the critical root zone, the inner quarter stays undisturbed, cut or fill in the inner half is limited to 4 inches, and at least half of the whole zone stays undisturbed.
Our guide to Austin’s tree rules explains how to measure a trunk, what the tree review asks for, and the order of the tree inspections.
Floodplain and creeks
A property inside the city’s 100-year floodplain, or within 100 feet of its edge, gets a floodplain review. The city is remapping its floodplains after the Atlas 14 rainfall study, and until that is done it regulates by the current FEMA 500-year floodplain, which is larger. Look your lot up on ATXFloodPro.
Remodeling, repairing, or altering a building in the floodplain takes a cost estimate of all the work. If you do some of the work yourself, the estimate still counts your labor as if you had hired it out.
A property within 100 feet of a creek centerline also gets an erosion hazard zone review.
Older houses
Changing or tearing down the exterior of a structure 45 years old or older triggers a historic review. So does work on a property in a National Register historic district, a historic landmark (H zoning), or a local historic district (HD).
Septic systems
On a lot with a septic system, adding conditioned space or bedrooms, or adding to the developed footprint with something like a pool, patio, or garage, triggers an on-site sewage facility review with Austin Water.
Sources: Residential Plan Review; Trees on Residential Property; Floodplain Management (City of Austin).
HOA rules and deed restrictions
Deed restrictions and HOA rules are private. The parties named in a restriction, such as a property owners’ association, enforce it, and unless the city is one of them, enforcement is a civil matter. City staff must approve a permit application that meets the Land Development Code even if it conflicts with a deed restriction.
A change in zoning should not undo a restriction that is enforceable now. A lot the HOME rules open to three units can still be limited by its deed restrictions.
So check before the application goes in. Search the Travis County Clerk’s official public records for the property with the keyword “Deed” or “Restriction,” and read the HOA’s governing documents for its own design approval steps. The city’s approval and the HOA’s are separate, and one does not stand in for the other.
Sources: Deed Restrictions and Development; Understanding the Development Process (City of Austin).
What happens before the application goes in
A complete application starts with the lot: who regulates it, what the zoning allows, and what is on it. On a home we build, we take care of the steps the application itself needs as part of preparing it. Checking deed restrictions and HOA rules stays with you, because the city’s approval does not depend on them. The list is here so you can see what is involved.
- Confirm the jurisdiction and zoning on the Jurisdictions Web Map, then in Property Profile for the zoning district, overlays, and Subchapter F.
- Check deed restrictions and HOA rules, as described above.
- Check the permit history in the public search of the Austin Build + Connect (AB+C) portal. If the property has expired permits, an Acknowledgment of Expired Permits goes in with the application.
- Get an address for each new unit. An ADU or other new dwelling unit needs its own address or building number from Address Management Services before the application goes in.
- Survey the trees on and next to the lot, using the city’s Residential Tree Review Checklist and tree survey samples from its trees page, so the regulated trees show on the plans.
- Look up the floodplain and creeks on ATXFloodPro.
- Check water and wastewater service. A remodel with three bathrooms or fewer needs no water and wastewater service plan verification (WWWSPV); a larger remodel uses one to show whether a new meter is needed. If it is, Austin Water’s meter process has to be finished before the permit can be activated.
- Ask questions early. The city offers short appointments for residential zoning and building code questions. Anything longer than 20 minutes takes a Preliminary Plan Review meeting, a paid meeting with plan reviewers before the application goes in.
- Open an AB+C account for the applicant, who uses it to pay fees and manage the application.
Sources: Residential Plan Review; Additional Dwelling Units; Trees on Residential Property; Austin Water Utility Permitting Office; Activating a Permit (City of Austin).
What goes in the application
The application is a web form for the project type: new construction or addition (ADUs included), interior remodel, garage conversion or carport and porch enclosure, total demolition, and others. Raising a roof counts as an addition.
What the plans need depends on the project, and Building Criteria Manual 4.4.0 has the full list. The common pieces:
- The application form for the project type. If information on it changes during review, a new, complete application goes in with the update.
- Floor plans drawn to scale, existing and proposed when walls, windows, doors, or plumbing fixtures are added or removed. They show room labels, wall measurements, ceiling heights, doors and windows, smoke and carbon monoxide alarm locations, new plumbing fixtures, handrails and guardrails, and room square footages. Legible hand drawings to scale are accepted.
- For new construction, foundation, wind bracing, and framing plans. Some projects, such as an interior remodel with no addition, can use a Structural Verification Report instead of structural drawings.
- Inside the Subchapter F boundary: a setback plane compliance plan showing topographic elevations, sealed by a Texas-registered professional land surveyor; a contextual site plan if you use setback averaging; and, for a project taller than 20 feet or more than one story, permit exhibits sealed and signed by a Texas-registered architect or a certified building designer.
- For a new dwelling unit with habitable space on the first floor, a visitability plan or waiver.
- The Acknowledgment of Expired Permits, if the property has any.
- For a tree review, the regulated trees shown on the plans.
- For work on an existing building in the floodplain, the cost estimate described above.
Sources: Residential Plan Review; Building Criteria Manual 4.4.0; Floodplain Management (City of Austin).
Plan review and the city’s targets
Review starts once the plan review invoice is paid; the city sends it after intake accepts the application. Reviewers take applications in the order received. When every review group has finished, the applicant gets an approval or a Master Comment Report listing what has to change, and every comment has to be resolved before approval.
The comments are answered in one update through the Modify a Residential Permit web form: a response to each comment, the full revised plan set with the changes marked, and any new documents, combined into one PDF. The city does not accept partial updates. From the second update on, it sends an invoice with the comment report, and unresolved comments can add fees.
When we take the permit on, we answer the comments and send the updates. If you or your architect submits the application, whoever submits it answers the comments, and we pull the permit as the general contractor once it is approved.
The city publishes a target for each round of its own review, in business days. A target covers one round, not the whole time from application to permit.
| Project type | City target |
|---|---|
| New construction and additions (ADUs included) | 10 business days |
| Interior remodel | 5 business days |
| Garage conversion or porch enclosure | 5 business days |
| Total demolition | 5 business days |
| Relocation | 5 business days |
| Swimming pool or uncovered deck | 5 business days |
| Fence | 5 business days |
Updates are listed at 7 business days, though the update instructions on the same page say an update takes as long as the first submittal.
The list gives no total time from application to permit, and the city’s overview of the process says review usually takes more than one round of changes. Once every review group approves, the city creates the building permit and any trade permits, pending activation.
Sources: Residential Plan Review; Understanding the Development Process (City of Austin).
Activation and inspections
An approved permit has to be paid for and activated before work starts. Only a general contractor registered with the city, or a homeowner acting as the general contractor for their own permit, can pay for and activate a building permit.
On a home we build, we are the general contractor on the permit, so we activate it. The city holds the permit holder and the general contractor responsible for the order of inspections.
Texas issues no state license for general contractors, and anyone in Texas can be one. Electrical, mechanical, and plumbing permits are issued to a contractor licensed by the state for that trade, or to a homeowner who qualifies for a homestead permit for work on their own home.
Each inspection checks a stage of the work before the next stage covers it up, which is why the order matters. Your printed permit lists the inspections your project needs and their codes. Anyone listed on the permit can schedule one, in the AB+C portal or by phone.
City inspectors work Monday to Friday, 7 a.m. to 3 p.m. An inspection usually happens 24 hours after it is scheduled, and an inspector’s workload can push it to the next business day or 48 hours. The city publishes a checklist for each residential inspection on its Building Inspections page.
A new home or addition, stage by stage
Every city inspection works the same way
- Schedule it in the AB+C portal or by phone.
- The inspector checks the work.
- Pass: once every inspection for a stage passes, the next stage can start.
Fail or partial: fix everything the inspector noted, then schedule the same inspection again. An extra inspection can carry a reinspection fee.
The engineer who inspects the foundation, and on new construction the third-party wallboard inspector, are hired directly. The city’s foundation and wallboard inspections are then scheduled with the final group, with the reports uploaded to the permit or collected at the final building inspection.
-
Before work starts
The site is set up before construction starts.
- Permit posted where it can be seen from the street
- Address posted where it can be seen from the street
- A paper copy of the approved plans on site
- Erosion controls and tree protection in place : Where the project needs them.
-
Layout
Any pre-construction inspections the project needs, then layout once the forms are set or the footprint is marked out.
- Pre-construction inspections, where they apply : Where the project needs erosion controls, a pre-construction environmental inspection comes first. Where it needs tree protection, booking the layout inspection sets up a pre-construction tree inspection. On new construction on an infill lot, the city’s layout checklist requires 619 Pre-Con EV to pass before layout.
- 101 Layout : A new home or an addition needs a new survey of the lot.
-
Before the pour
What goes in or under the slab is inspected before the concrete.
- 300 Electrical slab
- 302 Electrical grounding : With the slab inspection. It has to pass before the house can get power.
- 500 Plumbing rough : Where plumbing runs below the finished floor.
- 501 Plumbing pre-pour : Where any plumbing is in the foundation.
- 621 Pre-pour tree : Where the project has a tree review.
- Exterior plumbing: water and sewer yard lines, sewer tap : Any time from the plumbing rough on, and done before the final.
-
Foundation
The city does not inspect the foundation.
- Engineer’s foundation inspection : Once the pre-pour inspections pass, a Texas-licensed engineer inspects the foundation. The city’s foundation inspection is then scheduled with the final group, and the sealed report is uploaded to the permit or collected at the final building inspection.
-
Framing
After the trade rough-ins are done and before insulation or wallboard goes up.
- 301 Electrical rough : It has to pass, or be done with only minor violations, before the frame group is scheduled.
-
Frame group, scheduled together on most projects
- 103 Framing
- 502 Plumbing top-out
- 400 Mechanical rough
- 605 Wildland-Urban Interface frame : On a lot in the Wildland-Urban Interface.
- 106 Fire-rated assemblies : Usually only townhouses, duplexes, and exterior walls that need a rating.
-
Insulation
After framing passes.
- 104 Insulation
-
Wallboard
Before any taping or floating.
- 105 Wallboard : On new construction a third-party inspector does it, and the city’s 105 is then scheduled with the final group. No taping or floating until it passes.
-
One-time inspections
Inspections by other city departments. Any that apply have to clear before the final building inspection can be scheduled.
- 610, 611 Temporary utilities and water tap (Austin Water) : Where the project needs a new meter, it goes in before these pass.
- Environmental
- Septic (on-site sewage facility)
- Tree
- Fire or Wildland-Urban Interface final
- Driveway and sidewalk
- Landscaping
-
Electrical final
Approved before the final group is scheduled.
- 305 Electrical final
-
Final group
Scheduled together, with the reports on site or uploaded to the permit.
-
Final group
- 111 Final energy
- 405 Final mechanical
- 521 Final plumbing
- Foundation (the engineer’s report)
- 105 Wallboard, where a third-party inspector did it
- 112 Final building
- Reports : Duct leakage, envelope leakage (new construction only), termite treatment, foundation, and wallboard, plus an impervious cover survey where one is required.
-
-
Final and certificate of occupancy
When the final building inspection passes, the permit goes to Final and the inspector issues the certificate of occupancy, or a certificate of compliance where that applies.
If you are remodeling
- Layout (101) comes before any work starts. A remodel of a non-complying structure has a pre-construction inspection (100) first.
- The before-the-pour inspections apply only where the work pours a slab or puts plumbing in or below the floor.
- If the house stays occupied, framing is a single inspection (103) instead of the frame group. It is needed when 128 square feet or more of interior or exterior wall covering comes off, or when structural framing members are added, removed, or changed.
- City staff or a third-party inspector can do the wallboard inspection.
- There is no envelope leakage report; that one is for new construction.
- A remodel with three bathrooms or fewer has no Austin Water 610 and 611 inspections.
Keep the permit active
A permit expires if 180 days pass without an inspection, and each passing inspection extends it another 180 days. Plan the work so an inspection passes at least every 180 days.
Sources: Activating a Permit; Homeowner's Permit; Schedule a Building Inspection; Building Inspections; Residential Inspections Process flowchart (PDF); Tree Protection and Erosion/Sedimentation Controls flowchart (PDF); Building Foundation Inspection Checklist (PDF); Building Wallboard Inspection Checklist (PDF); Austin Water Utility Permitting Office; Additional Dwelling Units; Certificate of Occupancy; Residential Building Plan Review and Permit fee schedule (PDF) (City of Austin).
The certificate of occupancy
The certificate of occupancy (CO) confirms the house is habitable for its legal use. Once the final building inspection passes and the permit goes to Final, the inspector issues it for new construction or a significant renovation. Depending on the scope, a project gets either a CO or a certificate of compliance. If yours does not arrive, the city’s certificate of occupancy page has an email address to request it.
A temporary certificate of occupancy (TCO) can let you move in, stock, or furnish the house before the final CO. A residential TCO needs a residential inspection supervisor’s approval first, the prerequisite inspections have to be complete before it is requested, and its fees go on the project’s active trade permits.
Sources: Certificate of Occupancy; Building Inspections; Additional Dwelling Units; Understanding the Development Process (City of Austin).
Fees beyond the permit fee
The city’s fees change, so we do not list amounts here. The Fees page has the current schedules, including the residential plan review and permit fees. The kinds of fees to plan for:
- Plan review fees, invoiced when intake accepts the application. Review starts once they are paid.
- Permit fees, set when the application is approved and paid at activation, separate from application fees.
- Additional review fees from the second update on, and fees that unresolved comments can generate.
- Reinspection fees. The permit fee covers one inspection of each required type, and the city charges for each extra inspection when the work was not ready, earlier corrections were not made, or the inspector could not get on site.
- Consultation fees for a Preliminary Plan Review meeting, billed at each review discipline’s hourly rate, for an extended appointment, or for extra staff time during review.
- Tree review and inspection fees, when a tree review applies.
- Austin Water meter, tap, and inspection fees for a new meter, and impact fees that depend on the meter size and when the lot was platted.
- TCO fees, if the project needs a temporary certificate of occupancy.
- A service fee for paying by credit card in the AB+C portal; paying online from a checking account avoids it.
Outside the city’s fees, plan for the professionals the project may call for: a land surveyor for a Subchapter F setback plane plan, a tree survey, engineering or design work, the engineer’s foundation inspection, and a third-party wallboard inspection on new construction. Ask each for a written quote before you apply.
Sources: Fees; Residential Building Plan Review and Permit fee schedule (PDF); Residential Plan Review; Austin Water Utility Permitting Office; Trees on Residential Property; Residential Inspections Process flowchart (PDF); Certificate of Occupancy; Additional Dwelling Units (City of Austin).
Official links
Every page this guide relies on:
- Residential Plan Review: Applications, the review groups and what triggers them, updates, review targets, and Subchapter F exhibits.
- Work Exempt from Building Permits: Work that needs no building permit, and the exceptions.
- Do I Need a Permit?: The city's interactive permit questionnaire.
- Homeowner's Permit: When a building permit is required, acting as your own general contractor, and permit expiration.
- Jurisdictional Matters: What the extraterritorial jurisdiction (ETJ) is and what the city regulates there.
- Jurisdictions Web Map: Whether a property is in city limits, the ETJ, or another jurisdiction.
- Travis County single-family home permit: The county permit for a home outside city limits in Travis County.
- Property Profile: A property's zoning, overlays, and whether it is inside the Subchapter F boundary.
- HOME Amendments: HOME Phase 1 and Phase 2, Subchapter F for single-family homes, and floor area counting.
- HOME Phase 2 Guide: Whether a lot qualifies for small-lot single-family use.
- Additional Dwelling Units: ADU minimums, the address step, activation, permit expiration, and the certificate of occupancy.
- Trees on Residential Property: Regulated trees, how to measure them, critical root zones, and tree permits.
- Floodplain Management: The regulatory floodplain and the cost estimate for work on a building in the floodplain.
- ATXFloodPro: The city's floodplain map lookup by address.
- Deed Restrictions and Development: How deed restrictions relate to city permits, and who enforces them.
- Travis County Clerk official public records search: Where the city's deed restrictions page sends you to search a property's recorded restrictions.
- Understanding the Development Process: The city's overview of the three phases, from planning to occupancy.
- Address Management Services: Requesting an address for a new dwelling unit.
- Austin Water Utility Permitting Office: Water and wastewater service checks, meters, taps, the 610 and 611 inspections, and utility fees.
- Austin Build + Connect (AB+C) Portal: Paying fees, checking status and permit history, and scheduling inspections.
- Building Criteria Manual 4.4.0: The full list of residential submittal requirements.
- Activating a Permit: Who can pay for and activate a permit, and how.
- Building Inspections: Inspection hours, checklists, one-time inspections, and the approved plans on site.
- Schedule a Building Inspection: Who can schedule an inspection, online or by phone, who is responsible for their order, and where the required inspections are listed.
- Residential Inspections Process flowchart (PDF): The order of residential inspections from layout to the final, the inspection groups, and the reports due at the final.
- Tree Protection and Erosion/Sedimentation Controls flowchart (PDF): The tree and erosion control inspections on a residential project, including the pre-construction tree inspection that booking layout schedules.
- Building Foundation Inspection Checklist (PDF): Why city inspectors do not inspect foundations, and the report due at the final building inspection.
- Building Wallboard Inspection Checklist (PDF): Who inspects wallboard on new construction and remodels, and no taping or floating before it passes.
- Certificate of Occupancy: The certificate of occupancy and the temporary certificate of occupancy.
- Fees: The fee schedules for fiscal year 2026-27, in effect from October 1, 2026, and payment options.
- Residential Building Plan Review and Permit fee schedule (PDF): The residential plan review, permit, and reinspection fees, linked from the Fees page.
Plan your Austin project with us
Email or call with the address and what you want to build.
On a home we build, the permit can be part of our work, from the first zoning check to pulling the permit as the general contractor.
- Email: hello@agc.design
- Phone: 512-200-3474